Type of Formwork | Removal Time Period |
Walls, columns, and vertical sides of beams | 24 to 48 hours as may be decided by the engineer-in-charge. |
Slabs (props left under) | 3 days |
Beam soffits (props left under) | 7 days |
Removal of props to slabs (Spanning upto 4.5 m) | 7 days |
Removal of props to slabs (Spanning over 4.5 m) | 14 days |
Removal of props to beams and arches (Spanning upto 6 m) | 14 days |
Removal of props to beams and arches (Spanning over 6 m) | 21 days |
Form | Summers | Winters (Temp <18° C) |
---|---|---|
Walls, columns and vertical faces of structural members | 24 hrs. | 48 hrs. |
Removal of props under-slab Spanning up to 4.5 m | 7 days. | 14 days. |
Removal of props under beams and arches spanning up to 6 m | 14 days. | 28 days. |
Soffit formwork to slabs | 3 days. | (props to be refixed after removal) |
Soffit to beams props | 7 days. | Props to refixed after removal. |