How to Find House Construction Cost

How to Find House Construction Cost

  • Basic / Ruf / Lumsum Calculation
  • Final Calculation
Read more

Basic / Ruf / Lumsum Calculation

Sr. No.Item of workPercentage of total work
1All Type Drawing1%
2Excavation in ordinary soil and concrete3%
3Foundation5%
4Construction up to plinth5%
5Superstructure in brickwork25%
6Roofing including waterproofing12%
7Flooring6%
8Wood-work, i.e., Joinery, doors, and windows13%
9Internal finishes6%
10External finishes5%
11Water supply5%
12Sanitary work5%
13Electrification5%
Total100%
Read more
Sr. No.Item of workPercentage of total workEnter Your House Area in Sq ft 
ConstructionRate per Sq ft700 (as per our area)1,500 (Working Area)
1All Type Drawing1%10,500
2Excavation in ordinary soil and concrete5%52,500
3Foundation6%63,000
4Construction upto plinth6%63,000
5Superstructure in brickwork25%262,500
6Roofing including waterproofing12%126,000
7Flooring6%63,000
8Wood work i.e. Joinery, doors and windows13%136,500
9Internal finishes6%63,000
10External finishes5%52,500
11Water supply5%52,500
12Sanitary work5%52,500
13Electrification5%52,500
Total100% ₹1,050,000 
Read more

Video tutorial for better understanding:

Final Calculation 

Read more
  • Excavation
  • Footing
  • Backfilling
  • Plinth
  • Anti Termite
  • Plinth Protection
  • Column
  • Slab Casting
  • Brick Masonry
  • In-Side & Out Side Plaster
  • Plumbing
  • Electrical
  • Flooring
  • Door & Window
  • In-Side & Out-Side Paint
  • Cleaning
  • Reinforcement Steel
Read more

How to Find Construction Cost as Below Sheet

Sr.No.Building ConstructionUnitRateQtyAmount 
1Excavation Cum 151.00 105.96 15,999.96
2Footing Cum 4,623.00 1.88 88,946.52
3Backfilling Cum 125.00 88.40 11,050.50
4Plinth beam Cum 4,819.00 3.89 18,745.91
5Anti- Termite Treatment Sqm 69.00 93.16 6,428.04
6Plinth Protection Sqm 410.00 24.53 10,057.30
7Column Cum 4,944.00 0.76 3,757.44
8Slab Cum 5,106.00 9.89 50,498.34
9Brick Masonry Sqm 1,150.00 13.06 15,019.00
10.1External Plaster Sqm 395.00 310.08 122,481.60
10.2Internal Smooth Cement Plaster Sqm 230.00 68.04 15,649.20
11PlumbingRmt 200.00 465.80 93,160.00
12ElectricalRmt 210.00 465.80 97,818.00
13Flooring Sqm 1,413.00 56.96 80,484.48
14.1Door Sqm 5,990.00 12.10 72,493.38
14.2WindowSqm 590.00 61.60 36,344.00
15.1Plastic Emulsion PaintSqm 214.00 174.03 37,242.42
15.2Apex paintSqm 128.00 451.19 57,751.68
16CleaningSqm 100.00 93.16 9,316.00
17Reinforcement Steel M.T. 56,753.00 4.85 274,968.29
Total Amount 1,118,212.05 
Read more
  • What is BoQ | BoQ Meaning | Advantages of BoQ | What is BoM
  • What Is Rate Analysis | Rate Analysis of Earth Work, Brick, Concrete and Plaster
  • What Is Construction Contract | Types of Engineering Contracts | Percentage-Rate Contract
  • Estimation for Building Works | Centre Line Method | Long and Short Wall or Out and in to in a method
Read more

Did you like this story?