Speed - reduces the total rotation time by almost half when compared to conventional construction techniques.
Requires less work - With a defined procedure and checklists to follow, this technology minimizes the need for skilled labor and also eliminates activities such as masonry and rendering activities that require a lot of work.
Seismic and Durable Resistance - Buildings are more resistant to seismic and more
Less maintenance - Mainly without construction joints and with free-flowing concrete used, this technology reduces the chances of infiltration, which results in negligible
Smooth Finish - The construction of the Mivan ensures uniformity, therefore, all walls and slabs have a smooth finish, which means that no additional plastering is required.
Larger carpet area - offers the possibility of removing more carpet area compared to traditional construction techniques.
Earthquake resistant - more earthquake resistant and safer in the event of a strong This is because the structures built using the Mivan are monolithic concrete structures that act as a single strong unit.
Load Capacity: The load capacity of the Mivan formwork is 7-8 tonnes per square meter. The Mivan formwork is light and weighs about 18 to 20 kg per square meter.
Hit Time: The impressive vertical formwork time (wall) is 12 hours after pouring or when the concrete strength reaches 2N / mm2 and the horizontal formwork (deck) is 36 hours after pouring or when the concrete strength reaches 10N / mm2.
Durability: As the Mivan formwork panels are made of structural quality aluminum alloy, they are very durable and resistant. A single component can be repeated about 200 times.
Cycle time: High construction speed can be achieved by this system, which means faster completion of the project. Approximately, the time required to lay the floor in 7 days using Mivan.
Other Components. Ad. The other components used excluding wall, beam and deck components are internal and external soffit corners, exterior and interior corners for wall panels.