Rate Analysis of Brick Masonry : September 2024

Introduction of Rate Analysis of Brick Masonry

Important Point in Rate Analysis of Brick Masonry

Read more

Measurement of Brick Masonry

  • From foundation to floor one level (Plinth level)
  • Plinth (floor one) level to floor two-level
  • Between both specified floor levels above floor two-level
Read more

Dednctioan of Brick Masonry

Dimensions ofΒ Brick Masonry

Read more

Rate Analysis of Brick Masonry

Sr No.DescriptionQtyUnitRateCost
Brickwork with best available local bricks in foundation and plinth in cement mortar 1:3 (1cement : 3 fine sand)
Cost for 10.00 Cu.m.
ALabour Charges
1Mate4.00Day350.001400.00
2Mason4.00Day700.002800.00
3Helper8.00Day500.004000.00
4Coolie2.00Day350.00700.00
BMaterial
Bricks (Size of brick = 190 mm x 90 mm x 90 mm)5000.00Day5.0025000.00
Westage of brick 5% Extra5%1250.00
Cement22.00Bag320.007040.00
Westage of cement 2% Extra2%140.80
Sand2.30Cu.m.13623132.60
Westage of sand 2% Extra7%219.28
CScaffolding 1% Extra1%365.63
DTransportation Cost 1%1%365.63
EOther Charges 2 % Extra2%731.27
FAdd for Water Charge @ 1% on Items Marked1%365.63
GAdd for Contractor's Profit @15% on Items Marked15%5484.51
Cost of 10.00 Cu.m.52995.36
Cost of Cu.m.5299.54
Round off Cu.m.5300.00
Read more

Calculation of Brick for Rate Analysis of Brick Masonry

Cement and Sand Calculation

Read more

Calculation of Cement

  • = 0.19 m x 0.09 m x 0.09 m
Read more
  • Cement Mortar = 1 Cu.m. (m3) - 0.7695 Cu.m. (m3)
Read more
  • = 0.306 x 0.25
  • = 0.07664125 cu.m. cement requirement
  • Cement in k.g. = volume x density cement
  • Cement in k.g. = 0.07664125 cu.m. x 1440 (1440 kg/m Density of cement for 50 k.g)
    • = 0.07664125 x 1440 = 110. 363 kg of cement of bag requied ment of cement in k.g.
    • = 110.363 / 50 (one cemnent bag weight 50 k.g. only) = 2.20 bag
  • So, 10 cu.m. brick work requirement of cement = 2.20 bag x 10 cu.m. = 22 bag
Read more

Calculation of Sand

  • =0.2299 Cu.m. requierd of sand for 1 Cu.m.
Read more
  • So, 10 cu.m. brickwork requirement of sand = 0.2299 Cu.m x 10 cu.m. = 2.299 cu.m.
Read more

Calculation of Brick Masonry for Labour

Waste in Brick Masonry

Read more

Extra Work Calculation in Rate Analysis of Brick Masonry

Brick Work Rate

Read more

Rate Analysis of Brickwork

  • Measurement
  • Materials
  • Labor
  • Equipment
  • Other expenses
Read more

Is Code for Brick Masonry?

Labour Rate for Brick Work

Read more

Brick Work Rate Per Cubic Meter

Brickwork Labour Rate

Read more

Brick Rate

Bbm Masonry Full Form

Read more

Non Modular Brick Size

Brick Masonry Rate Per Square Foot

Read more

Labour Cost for Brickwork

Brick Work Ratio

Read more

Size Stone Masonry Rate Analysis

Block Work Rate Per M2

Read more
  • Scaffolding Rate Per M3
  • Difference Between CPM and PERT | What Is CPM & PERT
  • What Is Honeycomb In Concrete | Cause | Cure | Type of Grouting
  • Difference Between One Way Slab and Two Way Slab | What is Slab
  • Difference Between Flexible Pavement and Rigid Pavement | What is Pavement | Type of Pavement
  • Detail of Beam Connection | Simple Framing Connection | Semi-Rigid Framing Connection | Rigid Frame Connection
Read more

Did you like this story?

Please share by clicking this button!

Visit our site and see all other available articles!

Civil-Jungles