What is Rate Analysis | Rate Analysis of Earth Work, Brick, Concrete and Plaster: September 2024

What is Rate Analysis?

  • Quantity of materials required per unit rate of work and its cost delivered at work site including first cost, freight, transportation, sales tax, and insurance charges as artists in question. In case when materials like cement, steel, stone chips, and bitumen are supplied departmentally, then profit on the cost of materials is not allowed, but the cost of carriages from godown to work site shall be added.
  • A number of labour or labour hours required to complete per unit rate of work and its cost.
  • Overhead or equipment and establishment charges required to complete per unit rate of work.
  • Profit while arriving at workable rates, the factors that are to be considered have already been described.
  • In this rate analysis, all civil items consider and all items for different rate analysis sum major rate analysis as per below.
    • Rate Analysis of Earth Work.
    • Rate Analysis of Brick.
    • Rate Analysis of Concrete.
    • Rate Analysis of Plaster.
Read more

Rate Analysis of Earth Work.

  • As per below rate analysis of earthwork
  • Earthwork in an excavation in all kinds of soil including banking in 20 cm layers and breaking clods, ramming and dressing up for the purpose of making embankments or filling up ground depressions, lead upto 50 m and lift upto 1.50 m.
  • As per CPWD minimum labour requirement of 1 cu.m. excavation man labour 0.21 per day and female labour 0.14 per day.
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor's Profit @15% on Items Marked.
  • All Calculation for read Click here.
Read more
Sr No.DescriptionQtyUnitRateCost
Details of cost for 28.34 Cu.m.
ALabour Charges
1Man Labour6.00Day400.002400.00
2Female Labour4.00Day350.001400.00
BOther Charges 2 % Extra76.00
CAdd for Water Charge @ 1% on Items Marked38.00
DAdd for Contractor's Profit @15% on Items Marked570.00
Cost of 28.34 Cu.m.4484.00
Cost of Cu.m.158.22
Round off Cu.m.158.00
Read more

Rate Analysis of Brick.

  • As per below rate analysis of brick
  • Brickwork with best available local bricks in foundation and plinth in cement mortar 1:3 (1cement : 3 fine sand)
  • Rate analysis of Brickwork minimum labour requirement 10 cu.m. as below Bhisti 1.80 nos, Coolie 10.00 nos, Mason 3.3 nos, and Helper 3.3 nos. this above labour calculation use experience also recommend by CPWD
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor's Profit @15% on Items Marked, Transportation Cost 1%, Scaffolding 1% Extra.
  • All Calculation for read Click here.
Read more
Sr No.DescriptionQtyUnitRateCost
Brickwork with best available local bricks in foundation and plinth in cement mortar 1:3 (1 cement : 3 fine sand)
Details of cost for 10.00 Cu.m.
ALabour Charges
1Baathist1.80Day350.00630.00
2Coolie10.00Day350.003500.00
3Mason3.30Day700.002310.00
4Helper3.30Day350.001155.00
BMaterial
1Bricks4940Nos5.0024700.00
2Cement21Bag280.005880.00
3Sand2.8Cu.m.850.002380.00
CScaffolding 1% Extra1%329.60
DTransportation Cost 1%1%329.60
EOther Charges 2 % Extra2%659.20
FAdd for Water Charge @ 1% on Items Marked1%329.60
GAdd for Contractor's Profit @15% on Items Marked15%4944.00
Cost of 10.00 Cu.m.47147.00
Cost of Cu.m.4714.70
Round off Cu.m.4715.00
Read more

Rate Analysis of Concrete.

  • As per below rate analysis of concrete
  • Providing and laying in foundations and plinth cement concrete 1: 5: 10 (1 cement: 5 coarse sand: 10 graded stone aggregate 20 mm nominal & 40mm size) excluding the cost of centering and shuttering.
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor's Profit @15% on Items Marked, Transportation Cost 1%,  Wastage Extra Total Cost of 5%.
  • All Calculation for read Click here. 
Read more
Sr No.DescriptionQtyUnitRateCost
Providing and laying in foundations and plinth cement concrete 1: 5: 10 (1 cement: 5 coarse sand: 10 graded stone aggregate 40 mm & 20 mm nominal size) excluding the cost of centering and shuttering.
Details of cost for 10.00 Cu.m.
ALabour Charges
1Baathist2.70Day350.00945.00
2Coolie6.00Day350.002100.00
3Balder9.00Day350.003150.00
4Mason0.5Day700.00350.00
5Helper0.5Day400.00200.00
6Mate0.4Day500.00200.00
BMaterial
Cement18.00Bag280.005040.00
Sand3.13Cu.m.850.002656.25
Aggregate6.25Cu.m.735.004593.75
CWastage Extra Total Cost of 5%5%961.75
DTransportation Cost 1%1%122.90
EOther Charges 2 % Extra2%245.80
FAdd for Water Charge @ 1% on Items Marked1%122.90
GAdd for Contractor's Profit @15% on Items Marked15%1843.50
Cost of 10.00 Cu.m.22531.85
Cost of Cu.m.2253.19
Round off Cu.m.2253.00
Read more

Rate Analysis of Plaster.

  • As per below rate analysis of plaster
  • Providing and laying in 12 mm thick plasterwork  1: 4 (1 cement: 4 coarse sand: 1) excluding the cost of with material.
  • All Calculation for read Click here. 
Read more
Sr No.DescriptionQtyUnitRateCost
Providing and laying in 12 mm thick plasterwork  1: 4 (1 cement: 4 coarse sand: 1) excluding the cost of with material.
Details of cost for 100.00 sq.m.
ALabour Charges
1Mason6.70Day700.004690.00
2Bhisti9.20Day400.003680.00
3Coolie7.50Day400.003000.00
BMaterial
Cement9.00Bag280.002520.00
Sand1.248Cu.m.850.001060.80
CWastage of Material 2%2%71.62
DScaffolding 1% Extra1%35.81
ETransportation Cost 1%1%35.81
FOther Charges 2 % Extra2%71.62
GAdd for Water Charge @ 1% on Items Marked1%35.81
HAdd for Contractor's Profit @15% on Items Marked15%537.12
Cost of 100.00 Sq.m.15738.58
Cost of Sq.m.157.39
Round off Sq.m.157.00
Read more

Rate Analysis of Civil Works

Rate Analysis in Civil Engineering

Read more

Define Rate Analysis

What Is Rate Analysis in Civil Engineering?

Read more

Rate Analysis Is Done for Finding

What Are the Pre-Requisites to Carry Out Rate Analysis?

Read more
  • Cost of Material.
  • Cost of Labor.
  • Cost of Equipment.
  • Overhead Charges.
  • Contractor’s Profit.
Read more

Rate Analysis in Construction

Civil Rate

Read more

Rate Analysis for Construction

Water Charges in Rate Analysis

Read more

What Is Rate Analysis in Construction?

Procedure of Rate Analysis

Read more
  • The cost of items of work = Material cost + Labour cost
  • Other costs included to the above cost of items of work are:
    • Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost
    • Transportation cost (if conveyance more than 8 km is considered.)
    • Water charges = 1.5 to 2 % 0f total cost
    • Contractor’s profit = 10 %
Read more

Requirements of Rate Analysis

  • To compare a project's cost with the project's sanctioned capital to take necessary action or regularization of excess or less cost.
  • To workout the budget of the construction project and control the cash flows at various stages of construction work.
  • To find out the irrational rates quoted by the contractors during tendering process.
  • To serve as the basic data in case of dispute between project owner and contractor.
  • For the purpose of tendering. In the case of tendering, the contractor may calculate cost of unit work involved in each construction activity for justified quoting of rates. The client may also require rate analysis to calculate the cost of a construction project.
  • To assess the requirements of quantities of labour, materials, machinery and capital to complete the project.
  • To optimize the use of labor, materials and machinery and to know the alternatives to optimize the resources.
  • To assess the rate of unit work from time to time for payment increase in material or labor costs or any deviations in work specifications, extra items of work to the contractor.
Read more

What Is Analysis of Rate?

Rate Analysis Definition in Civil Engineering

Read more

Contractor's Profit in Rate Analysis

Rate Analysis Is Defined as

Read more

Mention the Two Heads in the Analysis of Rates Mens

Labour Rate Analysis Civil Work

Read more

Unit Rate Analysis

Rate Analysis of Plaster

Read more

What Is Rate Analysis?

Analysis of Rates

Read more

Rate Analysis in Estimation

  • Item Breakdown
  • Quantity Determination
  • Rate Calculation
  • Cost Estimation
Read more

Rate Analysis for Civil Works

Rate Analysis Definition

Read more

Requirements of Rate Analysis

Analysis of Rates for Building Works

Read more

Procedure of Rate Analysis

  • Itemization
  • Quantification
  • Rate Calculation
  • Cost Analysis
Read more

What Is Rate Analysis in Estimation?

Civil Rate Analysis

Read more

Rate Analysis in Estimation and Costing

Explain Rate Analysis

Read more

How to Do Rate Analysis for Civil Works?

  • Rate Analysis
  • Rate Analysis of Concrete
  • What is Consistency of Cement
  • What Is Cement | Type of Cement
  • What Is Soundness of Cement Test
  • What Is Water Cement Ratio | Water-Cement Ratio and Concrete Strength | Role of Water in Concrete
  • What Is Unit Weight | What Is Density | What Is Unit Weight Material | Unit Weight Building Materials
Read more

Did you like this story?

Please share by clicking this button!

Visit our site and see all other available articles!

Civil-Jungles