Copies Rqd | ADMINISTRATION CHECKLISTTo be completed by Customer Service Centre | Complete✓ |
2 | Geyserview printout (contour plan) checked with Applicant for Correctness | |
1 | Green PIM/BC Master cover has been completed | |
1 | Site Inspection Card completed | |
1 | Applicant Inspection card complete | |
1 | Form 6 (Application for Code Compliance Certificate) attached to Applicant Inspection Card | |
| Form 2 administratively complete and front cover signed appropriately | |
Lodgment category cost for building consent is 4A with an additional inspection of ½ hour |
ApplicantS = SuppliedN/A= Not ApplicablePlease arrange an vetting appointment through customer services should you wish to lodge this application in person (2 copies of plans and any relevant specifications to be supplied with the application) |
Building Consent No. | Processor Name: |
Form 2 | Building Consent Application Form completed and signed | S | N/A | P | F | N/A |
Roofing is defined as “restricted building work”. The design must becompleted out by a Licensed Designer? | Y | N | P | F | N/A |
As this project is defined as “restricted building work” a Form 2A(Certificate of Design Work) must be provided. | Y | N | P | F | N/A |
Have all Licensed Building Practitioner’s been identified? | Y | N | P | F | N/A |
Site Plan | House plans or Geyser View plan can be used to meet this requirement, request representative from Customer Services to print 2 copies. (indicate area of re-roof on this plan)Owner / Address match Form 2? | S | N/A | P | F | N/A |
1 | Detail what type of roofing material exists | S | N/A | P | F | N/A |
2 | Details of the new of roofing material that is to be used- Tiles (concrete, metal)
- Membrane
- Iron (color steel, alloy, zincalume, galvanized)
- Underlay
| S | N/A | P | F | N/A |
3 | Roof pitch | S | N/A | P | F | N/A |
4 | Provide details of any new framing members- Purlin/batten X spanning mm
- Rafter X spanning mm
- Substrate
- Fixings
- Other structural members
- Treatment of any new members
| S | N/A | P | F | N/A |
5 | Provide flashing details that meet the roofing manufacturers requirements- Ridges
- Valleys
- Barge
- up stand
- Dormer junctions
- Stop ends – kick-outs
- Apron
- Under flashing to low pitch roofs
- Change in pitch flashing
- Parapets or handrail junctions or capping.
| S | N/A | P | F | N/A |
6 | Wind fixings | S | N/A | P | F | N/A |
7 | Bracing to meet NZS 3604 / NZS 1170 D(change of roofing product may result in the need to increase existing bracing)Detail both existing braces and the proposed (where the bracing is unknown provide new bracing to comply with the relevant building standard)Space, Plane, hip and valley or Gable end wall | S | N/A | P | F | N/A |
8 | Penetrations through roofing material- Terminal vents
- Chimneys
- Skylights
- Solar panels (water pipes)
| S | N/A | P | F | N/A |
9 | Gutters (are there to be any change to existing gutters or downpipes that are not a direct replacement? Moving location or number of downpipes?)- Gutter type
- Over flows
- Rainwater heads
- Downpipes
- Drains to soak hole
| S | N/A | P | F | N/A |
10 | Ventilation to roof/ceiling space (Membrane, enclosed or skillion roofs) | S | N/A | P | F | N/A |
11 | Any fire rating issues that need to be addressed e.g. eaves closer than 650mm to boundary clear light roofing no closer that 1.0m to boundary etc. | S | N/A | P | F | N/A |
12 | Domestic smoke alarm(s) detailed on floor plan (Refer to NZBC F7 for requirements within 3m of sleeping areas and on escape route of each level) | S | N/A | P | F | N/A |
Additional Fees | | | |
| Please be aware that additional fees may be applied after the lodgment deposit is paid, for inspections, processing, certificates, government levies and the like (discussed?). | Y | N | Mail |
RDC use onlyP = PassF = Non-compliance with the Building Code – further information required N/A= Not Applicable RDC staff to record reasons for decisions in the question text box |
Other considerations (waivers and modifications- alternative solutions, TL authors- - section 75, fire rating etc) |
|
GRANTING BUILDING CONSENT |
Sign the application form to grant the building consent once satisfied on reasonable grounds that if the building work was to be constructed in accordance with the approved documents, then compliance with the Building Code will be met. |
Ref: CPV07 V06 Issued: 21/12/2012 |