Flush Door Data for Rate Analysis
Requirement data Rate Unit
Rate Anlysis Door Qty Nos
L B
Door Size Meter
Labour Charges
Labour Charges for Door Frame making Sqm
Labour Charges for Fixing hardware Set
Labour Charges for Fixing of Door Sqm
Material Charges
Flush Door 28mm thick Sqm
Wooden Frame Cu.ft
Wooden bidding Rmt
Laminate 1mm thick Nos
Rubber door stopper Nos
Tower Bolt SS 150mm - 100mm dia.  Nos
Handle Set
Railway Hinges per door 102mm in SS. Nos
Fevicol Kg
 
Rate Analysis for Flush Door
Sr No. Description Qty Unit  Rate Cost
A Labour Charges
1 Labour Charges for Door Frame making Sqm
2 Labour Charges for Fixing hardware Set
3 Labour Charges for Fixing of Door Sqm
B Material
1 Flush Door 28mm thick Sqm
2 Wooden Frame Cu.ft
3 Wooden bidding Rmt
4 Laminate 1mm thick Nos
5 Rubber door stopper Nos
6 Tower Bolt SS 150mm - 100mm dia.  Nos
7 Handle Set
8 Railway Hinges per door 102mm in SS. Nos
9 Fevicol Kg
D Transportation Cost 5 %
E Other Charges 2 % Extra
G Add for Contractor's Profit @15% on Items Marked